Solved

Due to a New Government Regulation, a Project Change Is

Question 517

Multiple Choice

Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well. The project manager should:


A) follow the change process flow and notify the legal department after the change is implemented.
B) extend a formal invitation to the legal department representative to join the CCB.
C) hold a separate meeting with the legal department representative and ask for approval.
D) notify the legal department representative in the event of an upcoming audit.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge