Multiple Choice
Due to a new government regulation, a project change is required. The project manager evaluates the change and realizes a representative from the legal department will need to approve the change as well. The project manager should:
A) follow the change process flow and notify the legal department after the change is implemented.
B) extend a formal invitation to the legal department representative to join the CCB.
C) hold a separate meeting with the legal department representative and ask for approval.
D) notify the legal department representative in the event of an upcoming audit.
Correct Answer:

Verified
Correct Answer:
Verified
Q512: Team members have reported that meetings are
Q513: A project team has failed to deliver
Q514: Which of the following inherently affects quality
Q515: A key stakeholder asked several members of
Q516: On an OBS chart, there is a
Q518: A team lead informs the project manager
Q519: A project manager is trying to ensure
Q520: A project's key stakeholders have requested significant
Q521: A company recently discovered that it could
Q522: A critical issue has developed in an