Multiple Choice
A project's key stakeholders have requested significant changes that will affect the scope. To adjust the project scope, which of the following need to be changed? (Choose two.)
A) Cost performance parameter
B) Project schedule
C) KPI
D) Corrective action plan
E) WBS
Correct Answer:

Verified
Correct Answer:
Verified