Multiple Choice
Task B is not planned to start until Task A is completed. Task A is delayed and will not be completed on time. Starting Task B prior to Task A completing is an example of:
A) Managing change
B) Fast tracking
C) Rolling wave planning
D) Crashing
Correct Answer:

Verified
Correct Answer:
Verified