Multiple Choice
A senior developer abruptly resigned without notice. Because of the senior developer's expertise, the active task workload was substantial. This would likely impact the project's: (Choose two.)
A) environment
B) scheduling
C) requirements
D) quality
E) scope
F) budget
Correct Answer:

Verified
Correct Answer:
Verified