Multiple Choice
An active project has a CPI of 0.92. Which of the following can be determined?
A) The project is currently over budget.
B) The project has a budget surplus.
C) The project is ahead of schedule.
D) The project is behind schedule.
Correct Answer:

Verified
Correct Answer:
Verified