Solved

A Project Has a ??? of $850,000

Question 495

Multiple Choice

A project has a ??? of $850,000. The project manager has identified and documented that certain key applications were not included in the scope management plan. As reported, the CPI is 0.8, and the PMO allows only a 5% additional increment to the planned budget. Which of the following should the project manager do NEXT?


A) Add the required work to complete the project behind $892,500.
B) Evaluate the impact and justify adding new work to the project.
C) Obtain approval from the CCB.
D) Request a budget increase of $170,000.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions