Multiple Choice
A project has a ??? of $850,000. The project manager has identified and documented that certain key applications were not included in the scope management plan. As reported, the CPI is 0.8, and the PMO allows only a 5% additional increment to the planned budget. Which of the following should the project manager do NEXT?
A) Add the required work to complete the project behind $892,500.
B) Evaluate the impact and justify adding new work to the project.
C) Obtain approval from the CCB.
D) Request a budget increase of $170,000.
Correct Answer:

Verified
Correct Answer:
Verified
Q490: A project manager is determining a project's
Q491: Which of the following documents ensures two
Q492: A company hires an outside vendor to
Q493: An active project has a CPI of
Q494: A project manager was reprimanded for failing
Q496: Which of the following documents does a
Q497: A team member has completed a project
Q498: Which of the following primary factors are
Q499: A company just announced all third-party vendors
Q500: Which of the following make up a