Multiple Choice
An organization needs a vendor to provide a solution. The organization can only describe its goals but not how to accomplish the work. Which of the following types of procurement should be used?
A) Request for information
B) Request for quote
C) Request for bid
D) Request for proposal
Correct Answer:

Verified
Correct Answer: