Multiple Choice
A project sponsor asks if a construction project can be accelerated to meet a new timeline. The project manager analyzes the schedule and finds insufficient float to accommodate the new delivery date. If more resources are provided, which of the following strategies would BEST help to achieve the new date?
A) Fast track
B) Burn
C) Crash
D) Reduce durations
Correct Answer:

Verified