Multiple Choice
While preparing to plan a project, the project manager meets with the key stakeholders to determine the flexibility between the project constraints. Which of the following techniques should the project manager consider to reduce personal bias and increase buy-in?
A) Send the stakeholders a survey about the project constraints to complete anonymously
B) Watch and determine which constraint is most important
C) Compare the constraints two at a time and have the stakeholders vote on importance
D) Look at historical information regarding the flexibility preferences of key stakeholders
Correct Answer:

Verified
Correct Answer:
Verified
Q472: A company is hired to perform some
Q473: A project manager wants to ensure that
Q474: Which of the following project documents should
Q475: A critical stakeholder has requested additional status
Q476: Which of the following information does the
Q478: A project team member highlights to the
Q479: A program manager informs a project manager
Q480: A project manager is planning to hold
Q481: A project manager wishes to track a
Q482: A project manager must create documentation before