Multiple Choice
A project manager wishes to track a project's performance against the original approved schedule. Which of the following steps is necessary to capture the needed information?
A) Determine the critical path.
B) Determine the milestones.
C) Set phase gates
D) Set a baseline.
Correct Answer:

Verified
Correct Answer:
Verified
Q476: Which of the following information does the
Q477: While preparing to plan a project, the
Q478: A project team member highlights to the
Q479: A program manager informs a project manager
Q480: A project manager is planning to hold
Q482: A project manager must create documentation before
Q483: Which of the following job roles is
Q484: Which of the following describes how a
Q485: Which of the following are MOST likely
Q486: A part that is needed to complete