Solved

Risk ID 2 Has Occurred

Question 165

Multiple Choice

Risk ID 2 has occurred. Risk ID 2 has occurred.   Which of the following ways should the project manager update the risk register? A)  Add a column for probability and set risk 2 at 100% B)  Change the risk 2 response to backups restored C)  Change the risk 2 status to issue D)  Change the risk 2 owner to PM Which of the following ways should the project manager update the risk register?


A) Add a column for probability and set risk 2 at 100%
B) Change the risk 2 response to backups restored
C) Change the risk 2 status to issue
D) Change the risk 2 owner to PM

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions