Multiple Choice
A project team is spread between two countries on different continents. Which of the following factors are MOST likely to influence communication methods selected for the communication plan? (Select TWO) .
A) Interorganizational constraints
B) Personal preferences
C) Language barriers
D) Cultural differences
E) Confidentiality constraints
Correct Answer:

Verified
Correct Answer:
Verified
Q161: A project manager is successfully adhering to
Q162: Which of the following is a risk
Q163: Many questions have arisen regarding a newly
Q164: Which of the following shows projected project
Q165: Risk ID 2 has occurred. <img src="https://d2lvgg3v3hfg70.cloudfront.net/C1257/.jpg"
Q167: A PM receives notification that an issue
Q168: A company has determined it does not
Q169: A project sponsor wants to know which
Q170: Which of the following features describe a
Q171: A busy project manager has a diverse