    When Developing a Project Schedule, Which of the Following Resources
Solved

When Developing a Project Schedule, Which of the Following Resources

Question 428

Question 428

Multiple Choice

When developing a project schedule, which of the following resources is the BEST to estimate task duration?


A) Project manager
B) Project scheduler
C) Project team
D) Project sponsor

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q423: The Chief Executive Officer (CEO) has changed

Q424: Two parties are beginning conversations regarding the

Q425: A project manager is determining a project's

Q426: The PMO is confused by an entry

Q427: Which of the following tasks are responsibilities

Q429: A project manager has been assigned a

Q430: An organization is divided into three separate

Q431: A key team member found a new

Q432: A project team received a memo stating

Q433: Based on the table below: <img src="https://d2lvgg3v3hfg70.cloudfront.net/C1257/.jpg"

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines