A project team received a memo stating no one can come into the office for the rest of the week due to heavy forecasted rain. The projected team reviews the risk management plan and carries out the risk response. The memo that prompted the activation of the risk response is referred to as the:
A) risk owner
B) risk impact
C) risk review
D) risk trigger
Correct Answer:

Verified
Correct Answer: