Question 176

Multiple Choice

The quarterly financial statement has been released, and portfolios are losing funding for projects. Which of the following options are MOST appropriate to keep the project alive and on schedule? (Choose two.)


A) Shorten the project duration.
B) Reduce the features being released.
C) Request more time with a smaller project team.
D) Reduce quality control.
E) Ask for operational team support.