Question 172

Multiple Choice

A developer is experiencing constant project scope changes and reaches out to the project manager to discuss the situation. They agree the customer has requested multiple modifications to the core idea and now extra work may need to be performed. Which of the following approaches would BEST support on-time delivery considering these changes?


A) Strict change management controls
B) Regular Scrum meetings
C) Continuous requirements gathering
D) Regular milestone reviews