A Key Stakeholder Has Communicated a Significant Project Scope Change

Question 51

Multiple Choice

A key stakeholder has communicated a significant project scope change to the project manager. Which of the following actions should the project manager take FIRST?


A) Submit a change request to the CCB.
B) Implement the change to the project.
C) Determine the impact of the requested change.
D) Update the schedule to accommodate the change.