Multiple Choice
A team member learns that an assigned task is not due until the very end of the project. Moreover, the team member is not aware of any predecessor tasks dependent on completing the assigned task. Which of the following does the project manager use to decide if the team member can start the task later or earlier?
A) Review the PERT chart and evaluate if the task is a critical dependency.
B) Review the PERT chart and evaluate if the task is a discretionary dependency.
C) Review the PERT chart and evaluate if the task is a real dependency.
D) Review the PERT chart and evaluate if the task is an external dependency.
Correct Answer:

Verified
Correct Answer:
Verified
Q47: The project team is not comfortable moving
Q48: A project manager at a projectized organization
Q49: A customer has stated that meeting the
Q50: An organization wants assurance that the specialty
Q51: A key stakeholder has communicated a significant
Q53: Which of the following organizational structures uses
Q54: A project team is identifying, rating the
Q55: A project manager is collecting the number
Q56: A customer will have ongoing changes to
Q57: Task ID 3 did not start on