Multiple Choice
A company has completed its annual strategic planning session. As a result, several related projects, which will achieve the company's technological improvement goals, are identified. Which of the following BEST describes these projects?
A) Portfolio
B) Program
C) Deliverable
D) Outcome
Correct Answer:

Verified
Correct Answer: