Multiple Choice
A project team is overseeing the installation of a new reptile habitat at the local zoo. During execution, zoo personnel decides to house a different type of reptile that will require a different temperature range than the capacity of the installed system. The modification has been approved. Which of the following constraints are MOST likely to be affected? (Choose two.)
A) Quality because the existing system is now outside the threshold.
B) Requirements because this is a change to initial scope.
C) Cost because replacing the system incurs additional expense.
D) Schedule because this was an unscheduled task and will impact the timeline.
E) Stakeholders because they will need to understand the modification and provide buy-in.
Correct Answer:

Verified
Correct Answer:
Verified
Q321: Tasks A, B, and C have a
Q322: Which of the following documents will provide
Q323: A new corporate policy was approved that
Q324: Which of the following charts would indicate
Q325: The project sponsor wishes to implement a
Q327: A company has completed its annual strategic
Q328: A new stakeholder has joined the project
Q329: During a CCB, a SME evaluated the
Q330: A subcontractor has submitted design documentation on
Q331: A project team has determined it will