Multiple Choice
Which of the following describes risk mitigation?
A) The transfer of the risk to another entity or project inside or outside the organization, along with associated costs.
B) The understanding of the risk with a detailed explanation of how the project intends to address the potential for occurrence.
C) The quantification of the risk in terms of how much the risk could potentially cost the project or parent organization.
D) The weighting or prioritization of the risk against all other identified risks within this project or others associated with it.
Correct Answer:

Verified
Correct Answer:
Verified
Q271: A post implementation review is being performed
Q272: Which of the following elements should be
Q273: A project manager is informed that the
Q274: A team member has completed an assigned
Q275: Which of the following documents should be
Q277: Several team members report that meeting objectives
Q278: At a weekly project team meeting, it
Q279: When a risk event occurs, which of
Q280: During the execution phase, the project manager
Q281: A project manager is starting a project