A project is in the initiation phase. Which of the following tasks will take place during this phase?


A) Develop a WBS.
B) Define the project requirements.
C) Create a project charter.
D) Acquire the project resources.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q100: Which of the following risk strategies prevents

Q101: Which of the following analyses should a

Q102: Project status meetings have poor attendance. A

Q103: According to the communication management plan, the

Q104: Which of the following documents need to

Q106: A risk with a high probability and

Q107: A hurricane occurs in an area where

Q108: Which of the following is the BEST

Q109: On larger projects, a vendor may occasionally

Q110: Which of the following are characteristics of

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines