Multiple Choice
A risk with a high probability and medium consequence to a project has been identified. In response, the project manager has purchased an insurance plan with the intent to provide additional funds if the risk is realized. There is no risk to the schedule or scope. Which of the following types of risk strategies is this an example of?
A) Accept risk
B) Transfer risk
C) Mitigate risk
D) Exploit risk
E) Avoid risk
Correct Answer:

Verified
Correct Answer:
Verified
Q101: Which of the following analyses should a
Q102: Project status meetings have poor attendance. A
Q103: According to the communication management plan, the
Q104: Which of the following documents need to
Q105: A project is in the initiation phase.
Q107: A hurricane occurs in an area where
Q108: Which of the following is the BEST
Q109: On larger projects, a vendor may occasionally
Q110: Which of the following are characteristics of
Q111: A client has provided a list of