Multiple Choice
Gas prices were included in the cost baseline for a transportation and hauling project. Although the estimates used to create the baseline were based on historical data, which of the following should the project manager consider as a root cause for potential issues with cost overruns?
A) Requirements
B) Lessons learned
C) Budget
D) Environment
Correct Answer:

Verified
Correct Answer:
Verified