Solved

A Project Team Has Completed a Major Deliverable Earlier Than

Question 206

Multiple Choice

A project team has completed a major deliverable earlier than planned and wants to deliver it for testing. The team lead sends an email providing notice of task completion to the project manager. Which of the following describes how the project manager can increase the likelihood that the deliverable moves to testing?


A) Send an email to quality assurance and copy the project team.
B) Call a meeting to hand off the deliverable to quality assurance.
C) Hold a conference call to a review the next deliverable with the project team.
D) Send an email to the project sponsor and copy the project team.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions