Multiple Choice
Two technicians are asked to install a 6U server at location U25 in a 40U server rack. The rack has been properly stabilized to the floor. Which of the following tools would BEST be used to install the server?
A) A static strap.
B) A server lift.
C) A PDU.
D) A UPS.
Correct Answer:

Verified
Correct Answer:
Verified