A technician is asked to install three servers: a 1U, a 4U, and a 6U. Which of the following is the MOST correct order to install these servers starting from the top of the rack?


A) 1U, 4U, 6U
B) 4U, 1U, 6U
C) 4U, 6U, 1U
D) 6U, 4U, 1U