Multiple Choice
Given the following standards, calculate the number of full-time equivalents (FTE) needed:
One FTE: 480 minutes per work day
Work standard: 30 minutes per request
Volume per day: 40 requests
FTE needed: ______________
A) 1.0
B) 1.5
C) 2.0
D) 2.5
Correct Answer:

Verified
Correct Answer:
Verified