Matching The Work Breakdown Structure Is the Basis for the Development

Question 1

Multiple Choice

Matching
The work breakdown structure is the basis for the development of three of the principal elements of the project delivery plan:
-Budget


A) a sequential array through time of all the tasks in the WBS and identifies when tasks should be executed, and the critical path through that array is defined as the longest sequence of tasks with no slack.
B) the delivery of the scope on schedule and budget analysed both quantitatively (known knowns) and qualitatively (known unknowns) captured in the threat register of the project.
C) provides a cost model of the project broken down by task and therefore sums to the total cost of the WBS to deliver.

Correct Answer: