​Which of the following is NOT a type of dependency between tasks on a PERT/CPM chart?


A) Resource mandatory
B) ​Project mandatory
C) ​External mandatory
D) ​Discretionary

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q22: ​The present value of $200,000 development costs

Q23: ​In Microsoft Project a task that indicates

Q24: Given the below figure,what is the Net

Q25: ​Given a project schedule with all tasks

Q26: ​A PERT/CPM is another name for a

Q28: ​A milestone task always has a duration

Q29: ​Good Project Communication Management requires techniques in

Q30: ​Given the below figure,when is the Breakeven

Q31: ​Given the below PERT/CPM chart,how many days

Q32: ​List and briefly describe the four objectives

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines