Multiple Choice
Given a project schedule with all tasks connected via one way arrows and with task durations. The critical path is ______.
A) the longest path through the network
B) the shortest path through the network
C) neither the longest nor the shortest path through the network
D) it cannot be determined
Correct Answer:

Verified
Correct Answer:
Verified