Multiple Choice
Use this information to answer the following questions.
Consider the following Activity-On-Node (AON) project (activity completion times are in days) .
-Refer to the figure.Suppose that additional resources are provided to crash the project completion time below its expected normal completion time.Which activities would be potential candidates for crashing?
A) B
B) D
C) A and B
D) A and D
E) F
Correct Answer:

Verified
Correct Answer: