Essay
Use this information to answer the following questions.
Consider the following set of activities.
-Refer to the information above.Assume that that time required to complete each activity is as follows.
a.Calculate the slack for each activity.
b.Calculate the earliest and latest start and finish times for each activity.
c.Determine the critical path.
d.Determine the length of the project.
Correct Answer:

Verified
Correct Answer:
Verified