Multiple Choice
When you create subtasks, the tasks associated with those subtasks automatically get
A) the duration of the longest subtask.
B) the dependencies of the subtasks.
C) the total of the subtasks' durations.
D) the subtasks' ancestors.
E) the predecessors of the subtasks.
Correct Answer:

Verified
Correct Answer:
Verified