menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Computing
  3. Study Set
    Modern Systems Analysis
  4. Exam
    Exam 3: Managing the Information Systems Project
  5. Question
    If an Activity's Optimistic Time Is 4 Weeks,its Realistic Time
Solved

If an Activity's Optimistic Time Is 4 Weeks,its Realistic Time

Question 37

Question 37

True/False

If an activity's optimistic time is 4 weeks,its realistic time is 6 weeks,and its pessimistic time is 8 weeks,then its estimated time would be 6 weeks.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q32: What would be the estimated time for

Q33: Microsoft Outlook is an example of project

Q34: Within the context of the SDLC,project closedown

Q35: A slipped completion date for an activity

Q36: Rework is not normally part of an

Q38: The project workbook serves as a repository

Q39: Managing the project team for effective team

Q40: Creating a work breakdown structure requires that

Q41: Task identification structure refers to the process

Q42: Skills that include defining and sequencing activities,communicating

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines