Multiple Choice
What would be the estimated time for completion if time estimates for programming are as follows: optimistic = 4 weeks;pessimistic = 6 weeks;realistic = 5 weeks?
A) 5 weeks
B) 6 weeks
C) 15 weeks
D) 3 weeks
Correct Answer:

Verified
Correct Answer:
Verified