    What Would Be the Estimated Time for Completion If Time
Solved

What Would Be the Estimated Time for Completion If Time

Question 125

Question 125

Multiple Choice

What would be the estimated time for completion if time estimates for installation are as follows: optimistic = 1 week;pessimistic = 1 week;realistic = 1 week?


A) 5 weeks
B) 6 weeks
C) 3 weeks
D) 1 week

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q120: Identifying,assessing,and managing the risks and day-to-day changes

Q121: Project time estimates for task completion and

Q122: Which of the following states correctly the

Q123: In order to determine the resources required

Q124: Project planning is the first phase of

Q126: A project can terminate naturally or unnaturally.

Q127: The amount of time that an activity

Q128: Pessimistic time is:<br>A)the maximum period of time

Q129: Which of the following is true regarding

Q130: _ are any person,group of people,piece of

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines