Which of the following is true regarding Gantt chart construction?
A) To construct the Gantt chart,a horizontal bar is drawn for each activity that reflects its sequence and duration.
B) To show precedence relationships,arrows are used to connect actions.
C) Arrows are used to reflect the sequence of activities.
D) Squares are used to represent activities.
Correct Answer:

Verified
Correct Answer:
Verified