Multiple Choice
Which of the following project management knowledge areas primarily involve generating, collecting, disseminating, and storing project information?
A) Project cost management
B) Project procurement management
C) Project time management
D) Project communications management
Correct Answer:

Verified
Correct Answer:
Verified