Multiple Choice
The technique for making cost and schedule trade-offs to obtain the greatest amount of schedule compression for the least incremental cost is known as _____.
A) dependency
B) crashing
C) critical chain scheduling
D) feeding buffers
Correct Answer:

Verified
Correct Answer:
Verified