Multiple Choice
Which of the following processes of project procurement management involves managing relationships with sellers, monitoring contract performance, and making changes as needed?
A) Closing procurements
B) Settling contracts
C) Deciding on the services to procure
D) Controlling procurements
Correct Answer:

Verified
Correct Answer: