Multiple Choice
An advantage of Design-Bid-Build is
A) it usually provides close to final pricing before the work begins
B) the Owner usually gets more for the money than other methods
C) quality is improved
D) schedule is minimized
Correct Answer:

Verified
Correct Answer:
Verified