Multiple Choice
Front-end loading costs on a project
A) is no longer done since the 2004 law banned it
B) can cause disruption of work
C) requires the Contract Administrator to be extra careful regarding costs and profits
D) Should be done whenever possible to maximize profits
Correct Answer:

Verified
Correct Answer:
Verified