    Estoppel
Solved

Estoppel

Question 10

Question 10

Multiple Choice

Estoppel


A) is a great way to force an Owner to pay promptly
B) requires previous acts to have set a pattern
C) is good for the Owner more than the Contractor
D) is one way to improve slow payment

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q5: quid pro quo<br>A) is no longer used

Q6: Unit Cost Contracts for the most part

Q7: A change order<br>A) affects cost<br>B) affects time<br>C)

Q8: There cannot be a Contract to commit

Q9: Pay when Paid clauses and Pay if

Q11: Lump sum is a common form of

Q12: Mistakes made preparing a bid proposal<br>A) are

Q13: Front-end loading costs on a project<br>A) is

Q14: A promise constitutes a Contract

Q15: Oral agreements prior to a Contract are

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines