If a stop notice is filed properly
A) the project has to shut down until a resolution is found
B) payments are withheld from the party identified as late in payments
C) the Owner has five days in which to rectify the situation
D) some but not all of the Contractors and Subcontractors on the site will be required to stop work until the critical issue is resolved