On Federal Work, a Lien May Not Be Permitted, So

Question 9

Multiple Choice

On Federal work, a lien may not be permitted, so


A) the Constructor cannot do a thing to rectify our situation
B) the Constructor has 48 hours after payment was due to file a lien
C) the Constructor has 72 hours after payment was due to file a lien
D) the Constructor files a stop notice

Correct Answer: