Multiple Choice
With a Differing Site Condition
A) the Contract Administrator needs to understand all the facts before alerting the Owner
B) cost will probably be more an issue than the schedule
C) timely notice by the Contractor to the Owner is important
D) the Architect will be to blame so dealing directly with the Owner is essential
Correct Answer:

Verified
Correct Answer:
Verified
Q4: In order to avoid responsibility, the Owner
Q5: Type I Differing Site Conditions should have
Q6: Acting conscionably means to act prudently in
Q7: Type II Differing Site Conditions<br>A) differ from
Q8: Type I Differing Site Conditions<br>A) differ from
Q9: If there is an exculpatory clause protecting
Q11: Differing Site Conditions usually refers to something
Q12: A force majeure is caused by natural
Q13: Through an exculpatory clause, an Owner will
Q14: A Type II Differing Site Condition is