Multiple Choice
Type II Differing Site Conditions
A) differ from what is shown on the drawings
B) differ from what a prudent Contractor would expect on the site
C) are typical on most projects
D) always cause a delay
Correct Answer:

Verified
Correct Answer:
Verified