Multiple Choice
Which one of the following statements best describes the critical path of a project network?
A) It is the sequence of activities between a project's start and finish that has the maximum amount of slack.
B) It is the sequence of activities that has the smallest normal activity cost.
C) It is the set of activities that has the smallest total number of predecessors.
D) It is the sequence of activities between a project's start and finish that takes the longest time to complete.
Correct Answer:

Verified
Correct Answer:
Verified
Q76: Seeking improvement in any one dimension of
Q77: If the length of the critical path
Q78: Evaluation methods used for projects with cash
Q79: Evaluation methods used for projects with predictable
Q80: The phase in which we hand over
Q82: Nonfinancial evaluation criteria may include risk tolerances,
Q83: Using the data supplied, if a decision
Q84: A(n) _ has specific goals, linked work
Q85: What is the project duration for the
Q86: Reducing project activity expected times or adding