Multiple Choice
Using the data supplied, if a decision is made to crash activity C, what is the cost for this one week of crashing?
A) $2,000
B) This activity cannot be crashed.
C) $3,000
D) $2,500
Correct Answer:

Verified
Correct Answer:
Verified